1
2
3
4
5
6
7
8
9
10
11
12
1

Deutschland

> 50 MW seit 2005

2

Frankreich

>30 MW seit 2014

3

Italien

> 1 MW seit 2008

4

Griechenland

> 2MW seit 2012

5

Großbritannien

> 20 MW seit 2016

6

Irland

> 0,1 MW seit 2014

7

Jordanien

> 60 MW seit 2015

8

Bahrain

> 3 MW seit 2017

9

Eritrea

> 0,2 MW seit 2013

10

Senegal

> 0,5 MW seit 2016

11

Malawi

12

Japan

Construction of a ground-mounted PV-System

Task: The engineering, procurement and construction of a 750kWp grid-connected ground-mounted PV-system
Location: Pruem, Germany
Size: 750 kWp
Period: 01/2020

Cathodic Corrosion Protection Expertise

Task: Assessment of corrosion on the foundation piles of an open-field PV-system and the production of an expertise on the site findings.
Location: Kunsisaki, Japan
Size: 2 MWp
Period: December 2018

More information about this project

Our expertise in the field of corrosion protection and prevention engineering is getting global attention, as our team has been contracted to survey and report on a case of cathodic corrosion eating at the foundation of a 2MWp open-field system in the state of Kyushu, Japan. Find out more about corrosion protection and prevention engineering  under our “Range of Services” page.

Expertise and Rehabilitation of an Industrial Roof-Mounted PV-System

Task: The surveying and reporting on the statical condition and variations of the PV-system, and then the planning, procurement and construction for the rehabilitation of the project
Location: Bad Hersfeld, Hesse, Germany
Size: 3,09 MWp
Period: October 2019

measurements in tramm, germany

Pull-Out Tests and Measurements

Task: Reporting an expertise on the findings from earth resistivity tests as well as pull-out tests and horizontal and vertical pressure tests executed on sample steel piles in preparation for the design of the mounting structure of a PV-system. E
Location: Tramm, Mecklenburg-Vorpommern, Germany
Size: 142,7 MWp
Period: September 2019

POT Villingen

Pull-Out Tests and Measurements

Task: Reporting an expertise on the findings from mechanical pull-out tests and horizontal and vertical pressure tests executed on sample steel piles in preparation for the design of the mounting structure of a PV-system.
Location: Villingen-Schwenningen, Bavaria, Germany
Size: 545 kWp
Period: August 2019

Corrosion Prevention Expertise for a Ground-Mounted PV-System

Task: The preparation of an expertise report for the prevention of corrosion, as part of pre-planning for the construction of a ground-mounted PV-System. The expertise included different solutions depending on project-specific factors, including a corrosion protection system in advance to building the system, offering 100% security against corrosion
Location: Neustadt, Hesse, Germany
Size: 750 kWp
Period: July 2019

Pull-Out Tests and Measurements

Task: Reporting an expertise on the findings from mechanical pull-out tests and horizontal and vertical pressure tests executed on sample steel piles in preparation for the design of the mounting structure of a PV-system.
Location: Samoussy, France
Size: 87 MWp
Period: April 2019

Restoration of a PV-Roof System

Task: The planning and execution of a stabilisation system for a slipping PV-industrial roof system.
Location: Kaiserslautern, Germany
Size: 1 MWp
Period: May 2019

Construction of an industrial PV-Roof System

Task: The engineering, procurement and construction of a 200KWp industrial PV-roof system
Location: Bingen, Germany
Size: 200 kWp
Period: 12/2017 till 02/2019

Rehabilitation and Re-Construction of a PV-System

Task: The dismantling of an industrial PV-roof system dismantled by a storm and its complete new planning, design and reconstruction
Location: Paderborn, Lower Saxony, Germany
Size: 350 kWp
Period: 11/2018 until 02/2019

EPC of a Ground-Mounted PV-system on a Conversion Area

Task: The engineering, procurement and construction of a 750kWp ground-mounted PV-system using a specially designed mounting structure
Location: Oberasphe, Hesse. Germany 
Size: 750 kWp
Period: 10/2018 until 12/2018

More Information about this project

The concept of conversion areas is to repurpose old or abandoned military, commercial or industrial areas in a mor modern and efficient way, or in this case, for a greener cause. These open-field areas are mostly reused for photovoltaic systems.

Sturmschaden an der Anlage in Bad Arolsen

Rehabilitation of a PV-System

Task: The rehabilitation and re-commissioning of a commercial PV-System damaged by a storm
Location: Bad Arolsen, Hesse. Germany 
Size: 1 MWp
Period: September 2018

Sanierung in Skegness - Bild der Anlagenkonstruktion

Stabilisation of a Ground-Mounted PV-System

Task: The design and structural stabilisation of a commercial open-field PV-system, which was at risk of failing by newly unaccounted-for weather conditions
Location: Skegness, Lincolnshire.United Kingdom
Size: 11 MWp
Period: August 2018

Anlagenstabilisierung - St. Austell

Stabilisation of a Ground-Mounted PV-System

Task: The design and structural stabilisation of a commercial open-field PV-system, which was at risk of failing on account of strong wind conditions
Location: Saint Austell. Cornwall, United Kingdom
Size: 3 MWp
Period: July 2018

Cathodic Corrosion Protection System for an Open-Field PV-System

Task: The design and implementation of a cathodic corrsion protection system which helped to guarantee the complete stoppage of corrosion that was heavily affecting the mounting structure of a commercial “10 MWp” open-field PV-system.
Location: Barnstaple. Devon, United Kingdom
Size: 10 MWp
Period: 05/ 018 until 06/2018

More Information about this project

After our team of specialists performed an extensive survey on this 10MWp solar farm in the west of England, we were contracted for and delivered on a cathodic corrosion protection system that guaranteed, for a period over 40 years, that the mounting structure of the existing PV-system would completely seize to corrode and any other metal driven into that field. Ache Engineering delivered a qualitative stabilisation system according to the time schedule.

Corrosion Assessment Expertise for a Ground-Mounted PV-System

Task: The preparation of an expertise report on the findings of specific tests and earth resistivity measurements done on a ground-mounted PV-System. This expertise contained a detailed and skilled assessment of the corrosion occuring on the foundation piles of the mounting system
Location: Barnstaple. Devon, United Kingdom
Size: 10 MWp
Period: 03/ 016 until 06/2016

Battery Rack System: For Samsung Batteries

Task: The design and construction of a 13-Level (4,6 kWh per level), total 60 kWh, battery rack system.
Location: Hesse, Germany
Size: 60 kWh
Period: April 2018

Stabilisation of a Industrial Roof-Mounted PV-System

Task: The design and implementation of a stabilisation system to prevent the slipping-off of a roof-mounted PV-system.
Location: Gundelfingen an der Donau, Bavaria, Germany
Size: 200 kWp
Period: 03/2018

Corrosion Assessment Expertise for a Ground-Mounted PV-System

Task: The preparation of an expertise report on the findings of specific tests and earth resistivity measurements done on a ground-mounted PV-System. This expertise contained a detailed and skilled assessment of the corrosion occuring on the mounting system
Location: Al Dur, Bahrain
Size: 3 MWp
Period: March 2017

Rehabilitation of an Open-Field PV-System

Task: The design and implementation of a structural rehabilitatio system for the mounting structure of an open-field PV-system
Location: Plymouth, Devon, United Kingdom
Size: 3 MWp
Period: 10/2017 until 12/2017

More Information about this project

Stabilisation of a PV-System near Plymouth (UK)

After being able to assert ourselves as a specialist in this field in an international tendering process, for stabilising an existing plant near the South English town of Plymouth. The more detailed planning phase began in our company headquarters in Leun (Hesse). The task was to stabilize an existing photovoltaic system, as it had become necessary due to the special weather and environmental conditions.

After analyzing the situation together with the customer we jointly decided on a solution in which further posts were anchored in the ground and mounted to the existing system with a special strut designed by Ache Engineering.

After performing a new and more detailed static calculation and several testings, we started to carry out the works in October. It was a challenge due to the difficult conditions on the ground, but turned out to be more of an opportunity. “The upper soil layers are very soft and squashy and the weather is very wet and stormy. These are not the best conditions for such works, but everything is going according to plan and we are well in time”, said Managing Director Ernst-Günter Ache. “Nevertheless, we were able to carry out the work to the complete satisfaction of our customer, who have already planned further collaborations,” he continues.

The on-site construction management and catering was also met with a very positive response: the food and the entire catering of our construction site kitchen was highly praised and the work carried out in the debriefing with the customer and client was exceptionally good.

We are always pleased when our services exceed the expectations of our customers. We’re glad about that and look forward to the future cooperation.

Ground-Mounted Solar Park in Ma’an, Jordan

Task: Management services for the construction of an open-field solar park in the dessert of MA’an, Jordan
Location: Ma’an, Jordan
Size: 66 MWp
Period: 11/2015 until 07/2016

Roof-Mounted PV-System

Task: Engineering, procurement and construction of an indsutrial roof PV-plant
Location: Schöffengrund, Germany
Size: 300 kWp
Period: May 2015

Roof-Mounted PV-System

Task: Engineering, procurement and construction of an indsutrial roof PV-plant
Location: Alzenau, Germany
Size: 300 kWp
Period: July 2015

Roof-Mounted PV-System

Task: Engineering, procurement and construction of an East-West PV-system mounted on an industrial roof, as well as operation and maintenance
Location: Weilburg, Germany
Size: 560 kWp
Period: April 2014

Roof-Parallel PV-System

Task: Engineering, procurement and construction of an indsutrial roof PV-system
Location: Küssaberg, Germany
Size: 92 kWp
Period: March 2013

Roof-Parallel PV-System

Task: Engineering, procurement and construction of an indsutrial roof PV-system
Location: Fleisbach, Germany
Size: 149 kWp
Period: August 2013

Roof-Parallel PV-System

Task: Engineering, procurement and construction of an indsutrial roof PV-system
Location: Deißlingen, Germany
Size: 999 kWp
Period: November 2012

Energy Optimisation

Task: Design and construction of an energy-saving filling plant for food products
Location: Bad Nauheim, Hesse, Germany
Period: November 2012

Roof-Parallel PV-System

Task: Electrical wiring of a roof-mounted 1 MWp PV- system.
Location: Aicha vorm Wald, Bavaria, Germany
Size: 1 MWp
Period: August 2012

PV-System – Industrial Roof

Task: Electrical wiring of a roof-mounted “2,3 MWp” PV- system
Location: Landsberg, Bavaria, Germany
Size: 2,3 MWp
Period: July 2012

Ground-Mounted PV-System

Task: Site Management for the construction and commissioning of a 1 MWp PV-system.
Location: Arnstadt, Thuringia, Germany
Size: 1 MWp
Period: June 2012

Heat Recovery System

Task: Diplom thesis and feasibility study for a heat recovery system
Location: Dillenburg, Hesse, Germany
Size: 500 kWp
Period: April 2012

Ground-Mounted PV-System

Task: Site Management
Location: Buettel, Schleswig-Holstein, Germany
Size: 34 MWp
Period: 11/2011 until 03/2012

Feasibility Study

Task: Conversion of an emergency generator into a modern cogeneration unit
Location: Schweinfurt, Bavaria, Germany
Size: 750 kWp
Period: June 2011

Self-Sufficient Off-Grid PV-System

Task: Construction and development of a self-sufficient electricity supply for a holiday home
Location: Kalamta, Greece
Size:Full coverage
Period: June 2011

PV-System: Roof-Mounted

Task: Engineering, procurement and construction of 8 different 200kWp PV-systems distributed on different roofs
Location: Pocio-Renatic, Italy
Size: 1,6 MWp (8x 200 kWp)
Period: November 2010

PV-System: Roof-Mounted

Task: Engineering, procurement and construction of an industrial roof-mounted PV-system
Location: Wetzlar, Hesse, Germany
Size: 149 kWp
Period: November 2010

Bild eines Verkehrsschildes

Self-Sufficient Electricity Supply

Task: Development of self-sufficient fuel cells for construction site trailers
Location: Germany-wide
Size: 36 kWh
Period: November 2010

PV-System: Roof-Mounted

Task: Engineering, procurement and construction of a roof-parallel 60 kWp PV-system integrated into a roof
Location: Mezzocorona, Italy
Size: 60 kWp
Period: October 2010

PV-System: Ground-Mounted

Task: Engineering, procurement and construction of a 200kWp PV-system on an open field
Location: Ponso, Italy
Size: 200 kWp
Period: September 2010

PV-System: Roof-Mounted

Task: Engineering, procurement and construction of a roof-parallel 200kWp PV-system on an industrial roof
Location: Pescanitina, Italy
Size: 200 kWp
Period: July 2010

PV-System: Roof-Mounted

Task: Engineering, procurement and construction of a roof-parallel 81 kWp PV-system on an industrial roof
Location: Gransee, Brandenburg, Germany
Size: 81 kWp
Period: July 2010

ACHE Engineering GmbH - Röntgenweg 9 - D-35638 Leun - Tel.: +49 (0) 6473-92254-0